Project Details
6 WGTP - Various
Buchanan Rd, Brooklyn - 8m 300MSCL
Lynch Rdm, Brooklyn - 14m 150 MSCLS
Misten Ave, Altona North - 150 MVCC
Muir Ave, Altona North - 150 CICL
Buchanan Rd, Brooklyn - 8m 300MSCL
Lynch Rdm, Brooklyn - 14m 150 MSCLS
Misten Ave, Altona North - 150 MVCC
Muir Ave, Altona North - 150 CICL
Completed (date)
Mar 20 to Sep 20
Client /Water Authority
West Gate Tunnel Project (CPBJH JV)
City West Water
City West Water
Water Authority Referee & Contact Number
Acciona - Anthony Pavilupillai - 0459 274 646
YVW - Joanna Middleton 0448981997
YVW - Joanna Middleton 0448981997
Project Details
Somerville Rd, Spotswood
DN150, Ecopur, 250m
DN150, Ecopur, 250m
Completed (date)
Mar-21
Client /Water Authority
West Gate Tunne Project (CPBJH JV)
West Gate Tunne Project
West Gate Tunne Project
Water Authority Referee & Contact Number
Aaron Bezzina (CWW) 0400 099 344
Glenn Watson (CWW) 0425 781 021
Glenn Watson (CWW) 0425 781 021